The Clarifier Project

HLA Project Number 10073C

Williams Charles West Construction of Kennewick, Washington, is under contract to replace the Mechanisms in the north and south clarifiers at the main wastewater treatment plant.

Equipment delivery began the week of June 18, 2012. WWTP staff began draining the south clarifier on June 16 in anticipation of the installation.

The contractor is progressing with the work on the south clarifier and expects to have the clarifier back in operation by the end of July 2012. Work effort will then switch to the north clarifier, and the installation should be completed by the end of August.

October Update

New photos of construction progress on the Clarifier Project.

  1. 1 Clarifier Pan
  2. 2 New equipment arriving on the truck June 18th
  3. 3 City crews finishing sludge removal in the old clarifier June 19th
  4. 4 Old Clarifier
  5. 5 Additional project photos July 18th
  6. 6 Additional project photos July 18th
  7. 7 Additional project photos – July 18th